|
||||||||
|
This contract involved the fit out of skirting, architrave, bathrooms and white goods to 299 apartments at 707 – 745 Anzac Parade, Maroubra, which commenced 25th July 2004 and finish February 2005. Although the project ran very smoothly we did encounter delays due to other trades on site trying to complete their works within time scales yet hampered by their own delays, (the domino effect). In some cases this meant leaving the task at hand and moving to another area or another job as the case may be, but where possible work around processes were put in place, with everyone working together. It also helped that a Millennium Carpentry Services Pty Ltd senior manager was on site to deal with any issues as they arose i.e. delays, industrial relation issues etc. |
||||||||
|
Pergola at Pacific Square Complex - Abi
![]() Supplied and installed pergola at the Children’s Playground, this job was completed within a one week time frame. |
||||||||
Although we were under pressure to complete the works within the contractual date we acknowledge this was achieved by the teamwork involved not only from Millennium Carpentry Services Pty Ltd employees but other trades on site and the rapport and respect they had for each other resulting in quality craftsmanship from all concerned to the end product. |
||||||||
|
|
||||||||
|
||||||||
| In May 2005 we were the principal contractor for the Dog Kennel Redevelopment at DMM, and a completion date of the 24th June 2005 was agreed. As with any project comprehensive safe work method statements (SWMS) were drawn up with particular reference to epoxy (hazardous substance) and supplemented by materials safe data sheets from the supplier (MSDS). | ||||||||
|
|
||||||||
|
DMM – Asbestos Project
|
||||||||
|
||||||||
| We were successful in being the preferred tender for this project in February 2005 which involved the removal of asbestos from various building at Kapyong Lines, Liverpool. The works included removing the old asbestos and replacement of new fc sheeting with ventilation panelling and replacement of electrical works, painting and replacement of ‘hazardous signs’ to doors etc., this involved working at weekends to ensure minimal disruption to staff. Because of the nature of the work involved we engaged specialised sub contractors for the safe removal and disposal of the asbestos who then supplied tipping dockets following the disposal of the asbestos to an approved tip site. Our sub contractors supplied their own SWMS, and during induction stage all SWMS were used for training and subsequently signed off by all employees and sub contractors working on the project, we then supplemented this by ensuring full attendance at tool box meetings to address any issues. back to top | ||||||||
|
PCG – Lecture Theatre Fit Out (Pfizer)
|
||||||||
|
||||||||
| This project was challenging as it involved a fit out to a lecture theatre, at 32 -42 Wharf Road, West Ryde. We constructed the floor area with laminated beams and plywood flooring and then acoustically soundproofed the area as per engineer’s drawings. However in order to complete this work within the time frame of the agreed contract and budget we had a team working 24/7 at different stages as the work demanded, which proved to be very successful. Again as with any work undertaken outside normal work hours we ensured that employees were fit and competent to carry out night work taking into consideration the upheaval to the body system, and ensured that time off complied with our enterprise agreement and Health & Safety guidelines. back to top | ||||||||
|
||||||||
| Due to a fire at the main storage area a new roadway for access to new a storage facility was requested and required our urgent attention. The project involved the design and construction of roadways capable of taking a 14 ton payload and the design and construction of bollards to withstand a 14 ton impact. We completed this project within a very tight time frame as we were able to utilise the services of some of our sub contractors in conjunction with re scheduling our own workforce to carry out the works as requested. All works were certified by a design engineer upon completion before sign off to DMM. back to top |
||||||||
|
||||||||
|
||||||||
|
As shown above the apartment fit out was very detailed and or involvement included the installation of skirting, architrave, white goods, and bathroom fittings. We kept within budget on this project by adhering to the MPX project plan and ensuring attendance at weekly site meetings thus addressing any issues on either side as they arose. |
||||||||
|
||||||||
|
Millennium Carpentry Services Pty Ltd has been involved with WGC with both the design and construction and to date we have been successful in contracting stage 1,2 and 3 with stage 1 and 2 completed and stage 3 ongoing, with a total completion to date of approximately 400 apts. |
||||||||
![]() View of Construction Site at Rhodes Waterside showing different stages in progress. |





.png)
.png)



Inside of Dog Kennels














